For those who are fed up with the 6-hour long journey between Delhi and Dehradun and are eagerly waiting for the opening of the much-awaited Delhi-Dehradun Expressway, there is a big and slightly disappointing news for them. Now you will have to wait a little longer to speed on this expressway. While earlier it was said to be opened in October 2025, now its new date has been announced. February 2026 Has been decided.
So why was there so much delay?
There is no negligence behind this delay, but a big and important instruction from the Prime Minister’s Office (PMO). PMO has clearly said that the expressway will not be opened in pieces. It will be inaugurated only when all its phases are completely ready, so that passengers can get a seamless experience.
National Highway Authority (NHAI) officials said another major reason for delay happened this year. monsoon rain Have told. Flooding in rivers due to heavy rains had stopped many security related works. In particular, important works like slope protection, tunnel finishing and installation of mobile towers are still pending in Dat Kali Mandir area near Dehradun, which is now targeted to be completed by November 2025.
When it opens, the 6-hour journey will be completed in just 2 hours.
The wait may have been long, but this expressway will completely change the travel experience.
- distance: Delhi-Dehradun journey through this 210 kilometer long expressway reduced from 6 hours to just 2 hours will remain.
- Cost: On this ambitious project approximately Rs 11,868 crore Expenses are being incurred.
- Route: This expressway will start from Akshardham in Delhi and reach Dehradun via Baghpat, Baraut, Shamli and Saharanpur.
How far has the work reached? (Progress report of 4 steps)
- First phase (Akshardham to Baghpat): This part was completed six months ago.
- Second phase (Baghpat to Saharanpur): This is also almost complete, only the finishing work is left.
- Third phase (Saharanpur bypass): The work of widening this old part is going on at a very fast pace.
- Fourth phase (Dehradun): This is the part where security and finishing work is still going on on the higher elevated section, due to which the project is getting delayed.
The specialty of this expressway, which makes it different from the rest
The biggest and unique thing about this expressway is that 12 kilometer long elevated corridorwhich will pass over Rajaji National Park.
- it Asia’s longest wildlife elevated corridor will be.
- To ensure that wild animals do not face any problem 6 Animal Underpass are also being made.
- Apart from this, it includes more than 100 underpasses, 5 railway overbridges and direct connectivity with many major expressways.
So, even though the wait has increased a bit, when this expressway opens, it will not only save time but will also present a great example of balance between engineering and environment.