Good News! The dream of speeding up Ganga Expressway will soon be fulfilled, 130 km stretch of Meerut-Badayun will open in November.

[ad_1]

Posts

The wait for the Ganga Expressway, which will give a new pace to the development of Uttar Pradesh, is about to end. There is a great news for those who are dreaming of driving their car on this expressway. The work is going on so fast that a large part of the expressway will be opened to the general public only in November 2024.

Travel from Meerut to Badaun will be easy

According to the information, first of all the 130 km long stretch from Meerut to Badaun will be opened for traffic. The construction work on this part is almost complete and the finishing work is going on at a fast pace. With the opening of this section, the journey from Western UP to Rohilkhand will become very easy and fast, which will save both time and money of the people.

What is the status of the entire project?

  • How much work completed: Till now, more than 80% work of the entire expressway has been completed.
  • Earthwork: More than 90% of the earthwork and subgrade work is complete.
  • Bridges and Structures: More than 95% of the bridges and other structures on the expressway are ready.

work is going on day and night

The work of building bridges on big rivers like Ganga and Ramganga is also almost in its final stages. More than 10,000 laborers and employees are working day and night to complete the project on time. The officials aim to open the entire expressway to the public before Mahakumbh 2025, so that the devotees coming for Kumbh do not face any problem in reaching Prayagraj.

This expressway will not only connect 12 districts of UP, but will also prove to be a milestone for the economic development of the state.