Flash

Mumbai-Ahmedabad Bullet Train update: NHSRCL casts first full height pier for high speed rail network

[ad_1]

This major construction milestone has been achieved despite
Image Source : NHSRCL WEBSITE

This major construction milestone has been achieved despite severe shortage of manpower and other logistical challenges because of ongoing Covid-19 pandemic and monsoon season. 

The National High Speed Rail Corporation Limited (NHSRCL) on Saturday said it has cast the first full height pier on the 508-km Mumbai-Ahmedabad High Speed Rail (MAHSR) project, popularly known as the Bullet Train project.

NHSRCL Spokesperson Sushma Gaur said the NHSRCL took a significant step forward in its construction work by casting the first full height pier near Gujarat’s Vapi at Chainage 167 on the Mumbai-Ahmedabad High Speed Rail Corridor which will run through 12 stations connecting Maharashtra, Dadar & Nagar Haveli and Gujarat.

“The average height of the pier on this corridor is nearly 12-15 metre and exact height of this pier is 13.05 metres, which is almost equivalent to a four-storey building,” she added.

 A look at a detailed operational plan of the Mumbai-Ahmedabad Bullet Train once project is completed

  Year 2023 2033 2043 2053
Train configuration 10 10/16 16 16
Number of rakes 24 24+11 44 71
Number of trains (per day/one-direction) 35 51 64 105
Train capacity 750 750/1250 1250 1250
Passenger seats (day/one direction) 17,900 31,700 56,800 92,900
Number of trains (per day/one direction) Peak Hour 3 4 6 8
Off peak 2 3 3 6

 

ALSO READChina launches first bullet train in Tibet, close to Arunachal Pradesh border

She said the pier was cast with 183 cubic metres of concrete quantity and 18.820 MT of steel. The special shuttering arrangement in the lift is one of the major features of the corridor providing better quality in eight hours, Gaur added.

“This major construction milestone has been achieved despite severe shortage of manpower and other logistical challenges because of the ongoing Covid-19 pandemic and the ongoing monsoon season in the region. There are number of such piers planned to be cast in coming months paving way for the first high speed rail corridor,” she said.

NHSRCL building India’s first high speed rail project

NHSRCL is the executing agency mandated with building India’s first high speed rail corridor between Mumbai and Ahmedabad.

Prime Minister Narendra Modi and former Japanese Prime Minister Shinzo Abe on September 14, 2017 had laid the foundation stone for the ambitious Rs 1.08 lakh crore ($17 billion) project. The bullet trains are expected to run at speeds of 320 km per hour covering the 508-km stretch in nearly two hours.

In comparison trains currently plying on the route take more than seven hours to travel the distance whereas flights take about an hour.

The NHSRCL has awarded several tenders for the construction of railway tracks, railway bridges, tunnels, railway stations and depots for the project till date.

(With inputs from IANS)

ALSO READMumbai-Ahmedabad Bullet Train: NHSRCL invites bids for Sabarmati depot construction

Latest India News



[ad_2]
Source link

Related Articles

Leave a Reply

Your email address will not be published. Required fields are marked *

Back to top button